Where to start renovating a house: the cheapest first step before you pay for plans

Written by Florian HofmannManaging Director · Updated October 2026 · 9 min read

Where to start renovating a house: get the idea checked and priced before you pay for full plans. Gather the floor plan, photos, your total budget and the Section 10.7 planning certificate. Have the changes sketched over the existing plan and checked against the planning rules, then ask a builder or quantity surveyor for a rough price, with each stage priced separately. Decide what to build, and only then pay for design and approvals.

The cheapest first step in renovating a house is a check and a rough price, before anyone draws a full set of plans. Have the idea sketched over your existing floor plan, checked against the rules and priced, then decide what to build.

Many owners start a first call with us knowing what bothers them about the house and having no idea what fixing it would cost. If that's you, this is where to start renovating a house in Sydney.

Where to start renovating a house when you don't know the cost

Do it in this order:

  1. Write down what doesn't work and what each room needs to do. Finishes can wait.
  2. Gather the papers listed below.
  3. Get the idea checked and sketched over the existing plan, including what nobody knows yet, such as whether a wall holds up the floor above.
  4. Get a rough price for the sketch, with each stage priced separately.
  5. Decide: go ahead, cut back, split it into stages, or stop.
  6. Only then pay for full design, consultants and approvals.

Steps 3 and 4 cost a small part of what step 6 does. Reversing the order is how owners end up with approved plans they can't afford to build; our guide to designing within a budget shows how.

An approval can also be for the wrong design. Everleigh, a Victorian terrace in Balmain, came to us already approved for a design buyers in the area wouldn't have wanted, so we reworked the plan around its character and the budget.

What should you gather before you call anyone?

Most of it is already in a drawer or on your phone.

What to gatherWhere to get itWhy it helps
A floor plan of the house as it isThe plan from when you bought, or a surveyIdeas are sketched over it
Photos of every room and the outsideYour phone, including ceilings, cracks and dampThe condition can be seen before anyone visits
Your total budgetWhat's available now, and what could come laterIt decides what gets sketched, and whether to stage it
The Section 10.7 planning certificateYour council, for a small feeZoning, heritage, flood and bush fire flags, and whether a CDC is possible (what it shows)
Plans of past approvalsCouncil records. The City of Sydney's archives hold building application plans from 1909 to 1997, searchable by addressHow the house was built. Check for an approval stamp: some plans were never approved
The strata plan and by-laws, in a strata schemeThe strata manager or owners corporationSome work needs the owners corporation's approval too
The insurer's scope of works, if your claim has oneYour insurer or its loss adjusterIt lists the repair work the insurer pays for

What does a renovation feasibility study check?

A renovation feasibility study tells you whether the idea works on this house before you pay for design, and marks the unknowns that change the price. The same unknowns come up on first calls again and again: whether a wall you want to remove holds up the floor or roof (how to tell if a wall is load bearing), where the waste pipe runs for a new toilet (moving or adding a toilet), and whether strata approval is needed. Until someone has looked on site, a price for those parts is a guess, so they go on the sketch as things to confirm.

Our feasibility study is that first check. We visit the property and check the planning controls for your lot, whether a CDC is possible or a DA is needed, heritage, flood and bush fire flags, the site itself and what your budget realistically buys, and we sketch the options. You receive a written summary: what's possible, the likely approval route, the risks and what still needs checking, a rough budget range for design, approvals and building, the reports and consultants you're likely to need, and your next steps in order, with a call to talk them through. It costs $1,200 + GST, takes 3 business days, and is credited against our design fee if you go ahead with us. The summary is yours to keep and use, whoever you work with next.

We've bought, designed and developed our own projects, so we design with build cost, approval and value in view. At Meridian in Leichhardt, the feasibility study showed that extending the federation house made more sense than a knockdown, so most of the original structure stayed. Our renovations and extensions page shows how design and approval run from there.

Can a builder price your renovation before there are plans?

Yes, as an estimate. A builder who does this kind of work can put a rough figure on a sketch, a list of the work and a site visit. The Australian Government's Your Home guide suggests getting preliminary estimates for each stage, so each one can be scheduled to suit the budget.

Ask for each stage on its own line, such as the kitchen and bathroom now and a second-storey bedroom later. Name your allowances (a mid-range kitchen, standard tiles) and give every builder the same information.

Read the result as a range. Your Home notes that builders' preliminary estimates "rarely come down, but they often rise", and a builder pricing early would like to win the job. A quantity surveyor prices from rates and quantities and has no stake in the building contract, which makes them the independent check.

How do you plan a renovation budget before you have plans?

Work from the total down: take out the costs before building and a contingency, and what's left is the build. CHOICE quoted an architect recommending a contingency of 15 to 20% for renovations; this example uses 15% of the build.

ExampleAmount
Total you can spend$260,000
Design, consultants and approvals (an assumption for this example)$35,000
Contingency, 15% of the build$29,000
What's left for building$196,000

Sydney homeowners have reported renovation quotes of about $4,000 to $6,500 per square metre in 2025 and 2026. At those rates $196,000 pays for roughly 30 to 49 m² of renovated floor, with kitchens and bathrooms at the top of the range. That is usually less than the wish list assumes, which is why the price comes before the design.

In our experience the architect's fee is only part of that $35,000, and often not the largest part: a survey, an engineer, reports, the certifier and council each look like a few thousand dollars and add up quickly. Our guide to architect fees in NSW lists each cost and what homeowners report spending in total. Allow for rent, storage and removals too, if you need to live elsewhere during the build.

Can you renovate in stages?

Yes, and it's often how a budget stretches to the whole house. Design the whole house once and build it in parts, so stage 1 doesn't block stage 2. If a second storey or another bathroom comes later, its structure, drainage and space are worked out now.

A later stage costs more. The builder sets up twice, finished rooms get disturbed, and prices rise: the Australian Bureau of Statistics measured a 5.2% rise in NSW house construction prices in the year to September 2026. If stage 2 needs approval too, ask whether both stages can go into one application and how long that approval stays valid.

What if an insurer is already repairing part of the house?

Sometimes an insurance claim and a renovation arrive together, and doing the work at once makes sense. It works best when the insured repair and your renovation stay separate on paper. Your policy decides what the claim covers.

Before anything is removed

Moneysmart advises taking photos and videos of the damage before anything is moved, and talking to your insurer before paying for temporary repairs. I wouldn't let anyone start demolition in the damaged area until the insurer has assessed it and agreed in writing, because demolition removes the evidence.

Two prices, kept separate

On larger claims the insurer's scope of works lists the repair work for the claim, and it can be reassessed once the walls are open. Ask your builder for one price that matches it and a separate price for your renovation. Then it's clear which costs belong to the claim and which are yours.

Repair or cash settlement

If the insurer selects and authorises the repairer, the General Insurance Code of Practice makes the insurer responsible for the quality of the work. With a cash settlement, your own builder can do the repair along with the renovation, but you manage it and the insurer doesn't guarantee it. The Insurance Council also warns that if the repairs are left unfinished, your insurance might not protect you against future events until a qualified person completes them. If there's a mortgage, talk to your lender first.

Timing

Under the Code (for insurers that have adopted it), the insurer tells you within 10 business days what it needs, updates you at least every 20 business days, and decides within 4 months of receiving the claim (up to 12 months in cases the Code lists). A revised Code went to ASIC for approval in October 2026; these timeframes apply until it starts. A CDC takes weeks and a DA months (see CDC or DA?), so the repair can't always wait for your approval, and Moneysmart warns that delays can lead to further damage the settlement won't cover.

What this means for you

  1. Write down the total you can spend, now and later.
  2. Gather the floor plan, photos and the 10.7 certificate.
  3. Get the idea checked and sketched, with the unknowns marked: walls, plumbing, approval, strata.
  4. Have a builder or quantity surveyor price it stage by stage, and treat the figure as a range.
  5. With an insurance claim, photograph everything, get the scope of works and keep two prices.
  6. Then choose who designs it. Our questions to ask an architect before hiring help with that first conversation.

Questions people ask

Can a builder quote without plans in NSW?

A builder can estimate from a sketch, a list of the work and a site visit, which is a sensible way to test a budget. A fixed price needs more. In NSW, residential building work over $5,000 (including GST) needs a written contract, and a contract over $20,000 must have the plans and specifications attached. If the work needs a DA, a construction certificate is also needed before building starts.

What are the stages of renovating a house?

For a renovation that needs approval: a check of the idea with a rough price, concept design, design development with the engineer, the approval (a CDC or a DA), construction drawings, pricing by builders, then the build. Each stage ends with a decision, and the first is the cheapest place to change direction. Small internal work may need no approval at all.

How does an insurance cash settlement work?

The insurer pays you an agreed amount instead of arranging the repair, and you organise the work. Where you have the choice, it must give you a Cash Settlement Fact Sheet with the options and a breakdown of the amount. You can get your own quotes, and you can ask for the settlement to be reviewed later, for example if more damage from the same event turns up.