Strata renovation approval in NSW: what the owners corporation must approve for a terrace or townhouse

Written by Florian HofmannManaging Director · Updated October 2026 · 9 min read

Strata renovation approval in NSW depends on the type of work. Cosmetic work, such as painting or new carpet, needs no approval. Minor renovations, including a kitchen renovation or changes to internal walls, need a majority vote. Work that is structural, external or waterproofed, or that touches common property, such as a bathroom, an enclosed balcony or an extension, needs a special resolution and usually a by-law. Council approval is a separate step.

Most renovations to a strata terrace or townhouse in NSW need the owners corporation's approval before work starts, and council approval is a separate step. Painting and carpet need nothing, a kitchen needs a majority vote, and a bathroom, a structural wall, an enclosed balcony or an extension needs a special resolution and usually a by-law.

Strata renovation approval in NSW works the same way for apartments, but terrace, townhouse and strata duplex owners tend to want the bigger jobs. A typical wish list from a terrace owner in a small scheme: enclose a back balcony, extend the kitchen into the courtyard, shift a wall and add a toilet upstairs, with a better stair to the roof later. Almost every item on that list needs a vote.

What renovations require strata approval?

NSW strata law sorts renovations into three types, each with its own approval and vote. This is how NSW Fair Trading sets out the current strata renovation rules:

TypeExamplesWho approvesVote neededWhat you provide
CosmeticPainting inside, carpet, hooks, handrails, blinds, curtains, built-in wardrobesNo approvalNoneNothing, but you repair any damage to common property
MinorA kitchen renovation, changes to internal walls, recessed lights, hard floors, wiring, reverse cycle air conditioning, double glazingThe owners corporation at a general meeting, or the strata committee if a by-law allowsMore than 50% of the votes castPlans, dates and times, your tradespeople's details, an acoustic certificate for hard floors
MajorMoving a structural wall, bathroom renovations, changes to the ceiling or the outside, work on common property, work that needs council approvalThe owners corporation at a general meeting onlySpecial resolution: no more than 25% of the value of votes cast againstA motion, plans, usually a registered by-law, and 14 days' notice before structural work

Your by-laws can add work to the cosmetic and minor lists, so read them first. Minor work becomes major as soon as it touches the structure, the outside or the waterproofing. When a job sits between two rows, we'd treat it as the higher one: an unnecessary vote costs a few weeks, while unapproved work can leave you paying to put the property back.

Is a kitchen or bathroom renovation minor or major?

A kitchen is usually minor. A bathroom is major.

Kitchens

Do you need strata approval for a kitchen renovation? Yes, as a minor renovation, while the work stays inside your lot: new cupboards, benchtops and appliances where the old ones were. It becomes major when the layout cuts into a structural wall, runs plumbing through the floor slab or a common wall, or pushes out into the courtyard.

Bathrooms and toilets

NSW Fair Trading lists bathroom renovations, including installing a new toilet or shower, as major work because they involve waterproofing. So adding a toilet to an ensuite needs a special resolution, even if the room stays the same size. Our guide to moving or adding a toilet explains why the waste pipe decides the cost.

Walls

Changes to internal walls are minor; moving a structural wall is major. In a terrace, the wall you want to shift can carry a floor, the roof or the stair, so ask an engineer first. See how to tell if a wall is load bearing.

How do you tell your lot from common property in a terrace or townhouse?

Your registered strata plan decides, with your by-laws. Ask the secretary for a copy, or buy one through an NSW Land Registry Services information broker.

Unless the plan says otherwise, walls drawn as thick lines are common property, and your lot stops at their inner face, the top of the floor and the underside of the ceiling. So the roof and the floor and ceiling structures are common property too. A courtyard or roof terrace may be in your lot, with a note limiting its height and depth, or stay common property.

The NSW common property memorandum, which a scheme can adopt, makes the owners corporation responsible for the slab between two storeys of the same townhouse, and for stairs inside a lot when the plan shows a separate level. Balcony walls, doors and railings are on the same list. If the plan leaves you unsure, treat the part as common property.

What does a terrace owner's wish list need?

That typical list, sorted:

What the owner wantsStrata approvalWhyCouncil or certifier
Enclose the back balconyMajor, with a by-lawChanges the outside; balcony walls are usually common propertyYes, a CDC or DA
Extend the kitchen into the courtyardMajor, with a by-lawNew structure; the courtyard can be common propertyYes, a CDC or DA
Shift a wallMinor, or major if it carries loadStructural work is majorIf structural or heritage listed
Add a toilet upstairsMajorWaterproofingInternal work can be exempt
A new stair to the roofMajor, with a by-lawCuts through the roof (common property)Yes, a CDC or DA

If a new room takes in common property, the strata plan itself may need to change, which needs a surveyor. See also can you enclose a balcony in NSW.

Should you get strata approval or council approval first?

They're separate approvals: the owners corporation decides about common property and by-laws, council or a certifier about planning and building rules. Work that council treats as exempt can still need a strata vote.

For anything major, strata comes first. City of Sydney, for example, asks for the owners corporation's consent, under its seal, with any DA that affects common property. For a CDC, ask the certifier what consent they need. The order that works:

  1. Get the strata plan and by-laws, and talk to the other owners.
  2. Have a concept design drawn.
  3. Put the special resolution and by-law to a general meeting, and get the owners corporation's consent for the DA.
  4. Lodge the DA or CDC. Our CDC or DA guide explains which one your work needs.
  5. Register the by-law, and give 14 days' written notice before structural work starts.

Ask for a by-law that allows for changes council requires, or a small redesign can mean another meeting.

How does a self-managed strata approve a renovation?

Without a strata manager, the secretary and the committee do the paperwork:

  • Send the secretary a motion (a short summary, your name and up to 300 words of explanation) with the plans and draft by-law, before the meeting notice goes out.
  • Every owner gets at least 7 days' notice of a general meeting, or 14 days for an AGM. Owners holding at least 25% of the unit entitlements can call a general meeting, which must be held within 14 days.
  • A general resolution counts one vote per lot. A special resolution counts unit entitlements, so in a row of six equal terraces, two owners voting no can stop it.
  • The secretary sends minutes to all owners within 7 days. The minutes are your approval, so keep them.
  • The by-law must be registered with NSW Land Registry Services within six months and has no effect until it is. Usually a solicitor or conveyancer lodges it.
  • For a DA, the seal goes on the owners corporation's consent in front of two owners it has chosen, or the secretary and another committee member.

For a by-law that gives you rights over common property, I'd pay a strata lawyer to draft it. NSW Fair Trading suggests the same where no model by-law fits.

What can the owners corporation ask for?

For a minor renovation, it can ask for the items in the table above and set reasonable conditions. If a by-law lets the committee decide, it must refuse in writing with reasons within three months, or the work is taken as approved.

For major work, expect the by-law to cover licensed and insured contractors, council approval before work starts, working hours, protecting and repairing common property, and who maintains the new work. The special resolution itself must say who maintains it.

Who insures and repairs common property?

The owners corporation must repair and maintain common property and insure the building. The building policy pays to reinstate the building to as-new condition, including the professionals the repair needs. Your contents are yours to insure, even when the damage came from common property.

When water comes through a shared wall, the wall, the pipes inside it and the balconies are usually common property, so the owners corporation organises and pays for the repair, through its building policy where the damage is covered. A leak from inside your own lot, such as under your sink, is yours. If the owners corporation failed to maintain something and that caused the damage, you have six years to claim damages from it. Our guide to balcony drainage and overflows explains how one balcony can flood the house next door.

If an insurance repair and your renovation happen together, the insurer pays to reinstate what was there. The rest is your cost and still needs approval.

Has strata renovation approval in NSW changed?

Yes, in stages. Since 1 July 2025, the committee's three-month deadline and the six-year limit for damages claims (up from two) have applied. A further Act passed in October 2026. When its renovation parts start, which NSW Fair Trading plans for 2027, minor renovations become "minor work": work on your lot that doesn't affect a building element, meaning the structure, waterproofing, fire safety systems, the building's outer skin and some services. Regulations will fill in the detail, so check the rules again when you apply.

What this means for you

  1. Get your strata plan and by-laws, and mark what is lot and what is common property before anyone draws.
  2. Sort your wish list into cosmetic, minor and major.
  3. Talk to the other owners early, with a sketch. In a small scheme, two votes can decide it.
  4. Get the strata vote and the owners corporation's consent before lodging a DA.

Before the vote, our feasibility study checks the planning controls for your lot, whether a CDC is possible or a DA is needed, heritage, flood and bushfire flags, and what your budget realistically buys. It costs $1,200 + GST, you get a written summary in 3 business days, and the fee is credited against our design fee if you go ahead. Our renovations and extensions page shows how a project runs from there.

Questions people ask

Do I need strata approval to replace a toilet?

Installing a new toilet is a bathroom renovation, which NSW Fair Trading lists as major work needing a special resolution. Swapping an old pan for a new one in the same spot, with no change to the floor, the waterproofing or the pipes in the walls, is a grey area the official lists don't name. Check your by-laws, then ask the secretary or committee in writing before the plumber starts.

Can strata refuse a renovation?

Yes. For major work the owners vote, and a special resolution fails if more than 25% of the value of the votes cast is against it. If you think a refusal is unreasonable, NSW Fair Trading offers free mediation, and the NSW Civil and Administrative Tribunal can order consent where approval was unreasonably withheld.

What happens if you renovate without strata approval?

You may have to pay to put the property back the way it was. If the work breaks the by-laws, the owners corporation can issue a notice to comply and take the matter to the NSW Civil and Administrative Tribunal, which can order the breach to stop and fine the owner.

Does a strata duplex follow the same rules?

Yes. A two-lot scheme, such as a strata-titled duplex, uses the same three types of work, but a special resolution needs both owners to agree. Once its two-lot changes start, the October 2026 Act will let these schemes decide by written resolution instead of holding meetings.