To compare builders' quotes, have every builder price the same drawings and specification, then read the quotes line by line rather than by their totals. When quotes for the same job are far apart, most of the gap usually sits in what each builder left out or turned into an allowance. The rest is margin, risk and how much each builder wants the job.
So a low quote can hide allowances that rise once you've signed, and the highest can turn out to be the only one that priced everything on the drawings.
Why do builders' quotes vary so much for the same job?
Gaps in the drawings
Builders price what is drawn and written down. Where the plans leave a choice open, such as the tiles or how the old floor meets the new one, each builder fills the gap with an assumption. NSW's consumer advice puts it bluntly: if you don't specify exactly what you want, the quote can include only the cheapest products and materials. Our guide to architect, building designer, drafter or builder compares how detailed each one's drawings usually are.
Allowances instead of prices
A PC (prime cost) item is an amount set aside for something you'll choose later, such as tapware. A provisional sum covers work nobody can price yet, such as rock in the excavation. Both are adjusted to the real cost, so a $15,000 kitchen allowance looks cheaper than a kitchen priced as drawn until you choose the kitchen. Our guide to provisional sums and PC items explains how they change.
The Australian Institute of Architects publishes a case where four builders priced one semi renovation. The highest was the only one that had fixed the cost of the joinery. The lowest, by a wide margin, carried the joinery as an allowance that could still rise.
What each quote leaves out
Common exclusions are asbestos removal, stormwater and sewer work, approval and certifier fees, landscaping, driveways, air-conditioning and sometimes GST. Each is a cost you'll pay someone else. In an older house, look hardest at asbestos: in NSW, removing more than 10 m² of non-friable asbestos, or any friable asbestos, needs a licensed removalist, and the wall sheeting of even a small bathroom can come to more than 10 m².
Preliminaries and site costs
Preliminaries are the cost of running the site: set-up, fencing, a toilet, scaffolding, bins, supervision and insurance. A 2025 Australian study found builders often overlook or underestimate them, and that the way they're priced can lead to significant differences between tender prices. Excavation, retaining walls and stormwater add more assumptions on a sloping or tight block.
Margin and risk
A fixed price includes the builder's margin and an allowance for the problems the builder must absorb once the price is fixed, so an old house with unknown footings attracts more of it. Housing Industry Association contracts also let the builder nominate a margin for variations, hidden site conditions and allowances that run over.
How much the builder wants the job
In our experience, a builder whose next year is already full sometimes prices high on purpose, and one short of work can price thin. NSW's guide to choosing a builder suggests asking what other jobs they're working on and who will supervise yours.
How to compare builders' quotes line by line
Get them to price the same job first
Give every builder the same drawings and revision, the same specification and a list of brands and models. NSW advice is to give at least three contractors the same information, send any change to all of them, and ask for a written quote listing all the work and materials.
A tender is the formal version: an architect or designer sends one package to several builders, and every answer to a question goes to all of them. The Australian Institute of Architects calls a competitive fixed-price tender the most common route for houses, with 4–6 weeks to price. You can run the same rules yourself.
What should a builder's quote include?
Every quote should answer these lines. Put yours side by side and check them in turn.
| What to compare | What to look for | Ask the builder |
|---|---|---|
| Exclusions | Every one, line by line | Is anything on the drawings left out of your price? |
| PC items | Each allowance against what you've chosen | What would my chosen tapware cost against this amount? |
| Provisional sums | What each covers, and how it was worked out | What is this figure based on? |
| Preliminaries | Set-up, fencing, scaffolding, bins, supervision | Is scaffolding included for the whole job? |
| Demolition and asbestos | Asbestos removal included, and on what test | Was the asbestos priced from a report? |
| Site works | Rock, retaining walls, stormwater, sewer, access | What happens to the price if you hit rock? |
| Approvals and fees | Who applies; certifier and council fees | Who pays the fees? |
| Margin | The rate added to variations and overruns | What margin applies to a variation? |
| Payment stages | Deposit 10% at most; stages that match the work | What share is due at frame stage? |
| Contract, time and GST | Fixed price or cost plus, which contract, start date, build time, GST | Have you changed the standard contract? |
A worked example: three quotes for one extension
Three quotes for the same rear extension with a new kitchen, in round numbers made up to show the method:
| Builder A | Builder B | Builder C | |
|---|---|---|---|
| Price on the quote | $318,000 | $347,000 | $372,000 |
| Kitchen | $15,000 allowance | $26,000 allowance | Priced as drawn |
| Asbestos removal | Excluded | Excluded | Included |
| Stormwater | $4,000 provisional sum | Included | Included |
| Add to match Builder C | $35,000 | $17,000 | Nil |
| Like-for-like price | $353,000 | $364,000 | $372,000 |
The additions assume the kitchen as drawn costs $34,000, the asbestos $9,000 and the stormwater $11,000, as Builder C priced them. The spread falls from $54,000 to $19,000. That $19,000 is the builder: margin, preliminaries, risk and appetite for the job. Weigh it against references, the build time, who will run the site and how each one answered your questions.
Is the cheapest quote the one to take?
Sometimes, once it's levelled. NSW's consumer advice lists a quote that seems extremely low compared with others as a warning sign. A builder who underpriced the job still has to make the numbers work, and that tends to show up as variations or slow progress.
If a builder has missed something, tell them before you sign. The Australian Institute of Architects warns that keeping quiet can cause the builder financial hardship and hurt the timing and quality of your project. I'd rather pay a fair price to a builder who can finish the job.
How do you compare a fixed price with a cost-plus quote?
A fixed price covers the work in the plans and changes only through variations and allowances. A cost-plus figure is an estimate: you pay the actual costs plus an agreed margin, and the risk of overruns sits with you. Ask the cost-plus builder for an estimate on the same scope, then compare the margin, what counts as a cost and how you'll be invoiced. In NSW, cost-based claims must be backed by invoices or receipts. If you're borrowing, ask your lender first, as many want a fixed price.
Which checks matter more than the price?
These come from NSW home building law. A solicitor can review the contract itself before you sign.
- The licence is current, covers this work, and its name and number match the quote and contract. A licence in a person's name doesn't let their company sign.
- For work over $20,000, you have the home warranty insurance certificate (officially home building compensation cover) before paying anything, deposit included, and you check it with the HBC Check.
- The deposit is 10% or less.
- Progress payments follow the work done, not the time on site.
- The price is on the contract's first page, with a warning if it can change.
What this means for you
- Put one package together: drawings, specification and brands. Settle the expensive finishes first: kitchen, bathrooms, windows and flooring.
- Ask at least three licensed builders to quote it by the same deadline.
- Level the quotes in the tables above.
- Do the licence and insurance checks before paying anything.
- If every levelled quote is over budget, change the design before you sign. Our guide on avoiding a design you can't afford to build shows what to cut first.
When we build, we give an itemised quote, as a fixed price or cost plus. If we've designed the interiors with you, the finishes are chosen before the price is set, so the quote carries real prices for them rather than allowances. Our Architecture for Homes page explains how a project with us runs, and a feasibility study tests what your budget buys before anything is drawn.
Questions people ask
How many quotes should I get for building work?
Three, which is what NSW advice suggests: give at least three contractors the same information so the quotes can be compared. A longer list rarely helps on a house. A detailed quote takes a builder days, and we find builders price more carefully when they know they're one of three rather than one of ten. Make sure every quote is for exactly the same drawings and specification.
Can a builder charge more than the quote?
Under a fixed-price contract, only in the ways the contract allows: variations, PC item and provisional sum adjustments, and any price clause the contract must warn about and explain. In NSW a variation must be in writing, signed by you and the builder, and show how the price change was worked out. If the extra work fixes the builder's own mistake, you don't pay for it.
Do builders charge for quotes?
Some charge for a detailed quote on a large job, because pricing a house properly takes days, and a builder asked to price before the design is finished can charge for that time. Agree in writing what you're paying for. Be careful about paying upfront for plans or other work before the building contract: NSW says that money is usually not covered by home warranty insurance if the builder fails.
Sources
- Getting quotes for contractors, NSW Government
- Contracts for residential building work, NSW Government, 29 April 2026
- Checklist for home owners signing a building contract worth more than $20,000, NSW Government
- Step by step guide to choosing the right tradesperson or builder, NSW Government, 22 July 2026
- Protecting yourself in case of builder insolvency, NSW Government, 1 September 2026
- Unlicensed asbestos removal, NSW Government asbestos website
- Single residential projects: types of tender (PDF), Australian Institute of Architects, 2022
- Single residential projects: tender process and builder procurement (PDF), Australian Institute of Architects, 2022
- How to determine builder's margin for HIA contracts, Housing Industry Association, 9 July 2024
- Challenges in pricing preliminaries costs for contractors: an Australian case study, Organization, Technology and Management in Construction, 2025